[edit] Update as of March 14, 2024
The Building Safety Regulator (BSR) has extended the deadline for registration of Building Control inspectors until 6 July.
Director of Building Safety for the Health and Safety Executive (HSE), Philip White, wrote on 14 March to the Building Control industry outlining new transitional arrangements for the registration of Building Control inspectors in England.
In Wales, the deadline has been extended until 1 October 2024.
Registered building inspectors are a new role created under the Building Safety Act 2022. They will be empowered to issue compliance notices and stop notices for higher-risk buildings during any stage of the design and construction process.
White wrote in his letter that Building Control professionals who had not yet completed a competence assessment can take advantage of the deadline extension provided they meet the following criteria:
- They are an existing Building Control professional;
- They are registered as a Class 1 Registered Building Inspector (RBI) by 6 April 2024;
- They are enrolled in, and in the process of having their competency assessed through, one of the BSR-approved competency assessment schemes by 6 April 2024; and
A scheme provider has not told them that they have not passed their competency assessment for a second time.
For more details, please visit the Making Buildings Safer website.
[edit] Definiton
Transitional arrangements are defined in the Government guidance "Eligibility for transitional arrangements in building control" updated March 11, 2024.
Transitinal arrangemants are described as allowing projects to stay under the existing building control regime – and avoid transfer to the Building Safety Regulator (BSR). Which means eligible projects can stay under the old rules. Though developers must take the required steps for their projects to qualify.
[edit] Details
If a project had building control arrangements established before October 1st, 2023, and has made substantial progress before April 6th, 2024, it qualifies for transitional provisions. A notice of sufficient progress must be given to the local authority in order to qualify
As such under these provisions, a project can continue to be regulated by the existing building control provider. This will require the building control provider to be appropriately registered with the BSR. In order to benefit from transitional arrangements, it is essential that notice is given to the relevant local authority, indicating that the building work has progressed sufficiently.
For the construction of a higher-risk buildings, sufficient progress means when pouring concrete for the permanent placement of foundations or piling has started. For work on existing buildings, this means when any work has begun. There is no specific rule for what counts as starting work, but it usually includes any significant building activity mentioned in the project application.
If the project involves an Approved Inspector (AI), a copy of this notice must also be goven to the AI as well. Failure to send notice to the local authority will result in the project transferring to the BSR.
Projects must use a suitably Registered Building Inspector (RBI) and suitable building control arrangements to continue benefitting from the transitional arrangements. Suitable building control arrangements means submitting full plans to the local authority. The plans must not be rejected. Or it means giving an initial notice to the local authority. The authority must accept the notice.
[edit] Related articles on Designing Buildings
- Building a safer future: proposals for reform of the building safety regulatory system.
- Building a Safer Future, Independent Review of Building Regulations and Fire Safety: Final Report.
- Building safety
- Building safety act 2022
- Building safety case.
- Building Safety Charter.
- Building safety certificate.
- Building safety in Wales.
- Building Safety Manager.
- Building Safety Regulator
- CIAT raises concerns about Building Safety Bill.
- CIOB reviews the Building Safety Bill.
- Competent person.
- Fire inspector.
- Fire Safety Act.
- Fire safety design.
- Fire Safety Order.
- Fire (Scotland) Act 2005.
- Golden thread.
- Grenfell articles.
- Hackitt Review.
- Health and safety for building design and construction.
- Health and safety plan.
- New Regulations published under Building Safety Act
- Reform of building safety standards.
- Risk assessment.
- Safety audit.
- Safety briefing.
- Safety management.
- The Building Safety Bill - A Quality Response.
- The Building Safety Bill and product testing.
- The Building Safety Bill, regulations and competence.
- The golden thread and BS 8644-1.
- What is a hazard?
- UK building control regime under the new Building Safety Act regulations
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.